監(jiān)理公司管理系統(tǒng) | 工程企業(yè)管理系統(tǒng) | OA系統(tǒng) | ERP系統(tǒng) | 造價(jià)咨詢管理系統(tǒng) | 工程設(shè)計(jì)管理系統(tǒng) | 甲方項(xiàng)目管理系統(tǒng) | 簽約案例 | 客戶案例 | 在線試用
X 關(guān)閉
軟件項(xiàng)目管理工具

當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具

礪志PMP模擬題每周精選4

申請免費(fèi)試用、咨詢電話:400-8352-114

Qustions 1:
As applied to projects, temporary means that--

a. Projects are short in duration
b. Every project has a definite beginning and end
c. The undertaking will end at an undetermined time in the future
d. Projects can be canceled at any time

Qustions 3:

Which of the following is an example a constraint in project plan development--

a. Records fo past performance
b. Financial reports from similar projects
c. A predefined budget
d. Lessons learned from prior projects

Qustions 5:

The management-by-objectives technique addresses all the following except--

a.Establishing unambiguous and realistic objectives
b. Periodically evaluating whether project objectives have been achieved
c. Promoting participation, team building, and commitment to the project
d. Establishing a specific career path for a project team member
 
Qustions 2:
All the following are examples of tools and techniques used in integration management except--

a. The work authorization system
b. Organizational procedures
c. Product skills and knowledge
d. Organizational policies

Qustions 4:

Performance measurement techniques are useful in overall change control because they --

a. Help show the status of the project
b. Measure overall project progress
c. Summarize information on the project for reporting to stakeholders
d. Help assess whether variances from the plan require corrective action

Qustions 6:

A work authorization system is a --

a.Work breakdown structure showing individual work elements
b.Formal procedure for sanctioning work so that it is done at the right time in the proper sequence
c.Method to ensure that each person on the project team knows the work elements that are his or her responsibility
d.System to help measure performance in terms of work completed versus work planned
發(fā)布:2007-03-02 10:57    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項(xiàng)目管理工具其他應(yīng)用

項(xiàng)目管理工具 禪道項(xiàng)目管理軟件 夢龍項(xiàng)目管理軟件 微軟項(xiàng)目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項(xiàng)目計(jì)劃軟件 項(xiàng)目進(jìn)度管理軟件 軟件項(xiàng)目管理工具 材料管理軟件 工程項(xiàng)目管理軟件系統(tǒng) 項(xiàng)目管理系統(tǒng) 施工管理軟件 建筑工程項(xiàng)目管理軟件 工程管理軟件