當(dāng)前位置:工程項(xiàng)目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項(xiàng)目管理工具
PMP認(rèn)證考試練習(xí)題及參考答案(三十二)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1 The utility of network-based schedules:A Reveals interdependencies.
B Facilitates "what if" exercises.
C Highlights critical activities.
D Provides information on resource requirements, time requirements and tradeoffs.
E All of the above.
ans:E
2 The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships. 來(lái)源:考試大
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
ans:C
3 The most common types of schedules are Gantt charts, milestone charts, line of balance, and:
A Networks.
B Time phased events.
C Calendar integrated activities.
D A and C only.
E B and C only.
ans:A
4 Scheduling is the process by which decisions are made concerning:
A Tasks to be accomplished.
B Personnel/organization that will be assigned to accomplish the task.
C Time when the tasks are to be completed.
D All of the above.
E A and C only.
ans:E
5 Time management is the allocation of time in a project's life cycle through the process of:
A Planning
B Estimating.
C Scheduling.
D Controlling 考試大(www.Examda。com)
E All of the above.
ans:E
6 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:
A $19K
B $21K
C $26K
D $29K
E indeterminate
ans:C
7 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A Become worse, become worse
B Become worse, improved
C Improved, increased
D Improved, become worse
E None of the above are correct
ans:B
8 The computation for Cost Performance Index is:
A BCWP/ACWP
B BCWP-ACWP 來(lái)源:www.examda.com
C BCWP-BCWS
D ACWP/BCWP
E ACWP-BCWS
ans:A
9 When comparing the cost of competing projects, which of the following is typically NOT considered?
A Opportunity costs.
B Direct costs.
C Sunk costs.
D Indirect costs.
E Burden rates.
ans:C
10 The Cost Performance Index (CPI) measures:
A cost of work performed vs planned costs.
B work performed vs cost of work performed.
C work performed vs planned work.
D direct costs vs indirect costs.
E floating costs vs. sunk costs.
ans:B
11 Parametric estimates are based on variables such as:
A Detailed planning and cost restraints.
B Physical characteristics and historical data.
C The WBS and similar projects. 來(lái)源:www.examda.com
D Project objectives and manpower allocations.
E Precise measurements and multiple inputs.
ans:B
12 Cost and schedule data are usually integrated because:
A optimized project cash flow can affect financial requirements
B they provide MIS with an integrated system to produce reports
C they control escalation allowances
D they account for omissions in the definitive estimate
E they predict future performance
ans:E
- 12015一級(jí)建造師《法規(guī)及相關(guān)知識(shí)》沖刺指導(dǎo)(10)
- 2壓力容器焊接接頭設(shè)計(jì)
- 32015年造價(jià)工程師考試《理論與法規(guī)》課程講義(12)
- 4IPMP申請(qǐng):IPMP認(rèn)證費(fèi)
- 5工程咨詢概論考點(diǎn):投資的定義與分類
- 62015年武威造價(jià)工程師報(bào)名入口
- 7工程造價(jià)精華50條(一)
- 82015招標(biāo)師考試項(xiàng)目管理考點(diǎn):變更與洽商
- 92015招標(biāo)師考試教材:合同的訂立與效力
- 10濱綏線牡丹江至綏芬河段擴(kuò)能改造工程某隧道(實(shí)施)施工組織設(shè)計(jì)
- 11農(nóng)遷房工程給水管網(wǎng)安裝施工組織設(shè)計(jì)50p
- 12造價(jià)工程師建設(shè)工程計(jì)價(jià)復(fù)習(xí)資料——我國(guó)與世界銀行的合作
- 13一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):正反循環(huán)鉆孔
- 14攪拌車發(fā)動(dòng)機(jī)常見的故障原因分析
- 152015年監(jiān)理工程師考試?yán)碚撆c法規(guī)練習(xí)題(58)
- 16名師達(dá)江解答二級(jí)建造師相關(guān)疑問——報(bào)名篇(六)
- 172012一級(jí)建造師《建筑工程》:地基基礎(chǔ)常見質(zhì)量通病
- 182015年咨詢工程師《工程咨詢概論》每日一練4.7
- 19山東煙臺(tái)西港區(qū)億噸大港 欲建世界最大碼頭
- 202015年招標(biāo)師考試《招標(biāo)采購(gòu)案例分析》模擬試題(4)
- 212015年招標(biāo)師考試《法律法規(guī)與政策》復(fù)習(xí)資料:第一章9
- 22中鐵建工集團(tuán)有限公司公開招聘公告
- 23某工程園林綠化施工組織設(shè)計(jì)
- 24咨詢工程師《宏觀經(jīng)濟(jì)政策與發(fā)展規(guī)劃》自測(cè)題(32)
- 252006年度全國(guó)監(jiān)理工程師資格考試建設(shè)工程監(jiān)理基本理論與相關(guān)法規(guī)試卷及答案
- 262015年一級(jí)建造師《工程經(jīng)濟(jì)》第三篇沖刺講義(5)
- 27某職工宿舍樓工程施工進(jìn)度計(jì)劃網(wǎng)絡(luò)圖(CAD版)
- 28西安某工程完整周期建設(shè)方進(jìn)度計(jì)劃
- 292015年一級(jí)建造師《公路工程》路面工程施工(2)
- 30世界貿(mào)易組織《政府采購(gòu)協(xié)議》的主要內(nèi)容
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓