當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
PMP認證考試練習題及參考答案(二十九)
1 Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
ans:A
2 The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF). 來源:www.examda.com
D Scheduled time (LF - ES).
E Event.
ans:D
3 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
ans:A
4 Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.
A 0.5
B 1
C 1.8
D 2.2
E 2.8
ans:C
5 In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks. http://ks.examda.com
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
ans:C
6 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A 8
B 8.8
C 9.1
D 9.7
E 10.5
ans:B
7 Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above 來源:考試大網(wǎng)
ans:E
8 All of the following are categories of a milestone in a schedule except:
A End date.
B Contract dates.
C Key events scheduled.
D Imposed dates.
E Task duration.
ans:E
9 The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
ans:D
10 Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
ans:D
11 The key purpose of project control is to:
A Plan ahead for uncertainties.
B Generate status reports.
C Keep the project on track.
D Develop the project road map.
E All of the above. 來源:考試大網(wǎng)
ans:C
12 Fast tracking means to:
A Speed up a project through parallel tasks.
B Swap one task for another.
C Reduce the number of tasks if possible.
D B and C.
E None of the above.
ans:A
- 1招標師職業(yè)水平考試:項目管理與招標采購第二章練習題35
- 22013年陜西二級建造師增項注冊申請表
- 310種心態(tài)助你順利通過2015年二級建造師考試
- 4西安危房改造將使6000農(nóng)戶圓“安居夢”
- 5二建復(fù)習資料基坑支護結(jié)構(gòu)變形監(jiān)測
- 6攪拌車向右跑偏是怎么回事?
- 7對攪拌車激烈加油、頻繁剎車的弊端
- 8【任性備考】網(wǎng)校名師真優(yōu)秀 一次通過二建有保障
- 92015安全工程師《生產(chǎn)管理知識》試題精選(12)
- 10城市橋梁工程施工方案的內(nèi)容
- 11造價工程師復(fù)習資料:各級編碼的代碼含義
- 122015監(jiān)理工程師考試《工程質(zhì)量與進度控制》模擬題(1)
- 13近兩年全國至少有32家上市宣布進軍養(yǎng)老地產(chǎn)項目
- 142015年招標師考試《管理與采購》復(fù)習材料(1)
- 15房地產(chǎn)腐敗窩案:一樓盤擊倒40多名干部 涉案金
- 16惠州市2015年造價工程師考試報名時間為6月8日-7月2日
- 17曲阜市強力推進小城鎮(zhèn)建設(shè)
- 182015年咨詢工程師《工程項目組織與管理》每日一練(3.21)
- 19強夯處理濕陷性黃土施工工法
- 20我國首座工程機械館長沙落成
- 21住宅產(chǎn)業(yè)化發(fā)展問題及對策
- 222015年安全工程師《管理知識》:職業(yè)病報告內(nèi)容
- 232015年招標師考試《案例分析》考前提高試題1
- 24金溫鐵路全線跨度最大隧道下岙一號隧道順利貫通
- 25某工程水暖系統(tǒng)施工組織設(shè)計 64p
- 26建筑工程現(xiàn)場施工經(jīng)驗——鋼筋綁扎的部分基礎(chǔ)知識(19)
- 27[浙江]隧道工程施工組織設(shè)計
- 282015年監(jiān)理工程師考試《建設(shè)工程合同管理》習題(20)
- 292015年咨詢工程師《工程咨詢概論》考前練習題(10)
- 302015年安全工程師《生產(chǎn)技術(shù)》:礦(地)壓的基本概念
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓