當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
PMP認證考試練習題(九)(中英文)
1. To be successful in a functional organization, the project manager must rely on:
Referent power
Formal authority
Informal power structure
Broad span of control
Both a and c
為在職能組織中取得成功, 項目經(jīng)理必須依賴于:
指令
正式的權利
非正式的權利結構
廣泛的控制
a 和 c
2.(PDM)The precedence Diagram Method (PDM):
Has only finish to start task relationships.
Has the activity on the node
Provides the flexibility of lead and lag time to the activities.
Uses standard deviation to assist in the probability of a duration of an activity.
B & c
邏順序圖法(PDM):
只有完成到開始任務的關系
在節(jié)點上有工序
提供工序領先和滯后的靈活性
使用標準偏差計算工序工期的可能性
B 和 c
3. The program evaluation review technique (PERT):
Typically has 3 time estimates to assist in the prediction of the expected value of activity duration.
Is event oriented with activity on arrow.
Will have only one time estimate per activity.
Is easy to prepare at minimal cost.
A & b
計劃評審技術(PERT):
典型的工序工期值的預計有3倍的估值
工序在箭頭的事件導向
每個工序將只有一次估計
很容易以最小成本準備
A 和 b
4. Resource leveling:
Deals with the effective use of resources through the project to minimize the resource time:
Typically tends to have no effect on the duration of the activities.
Tends to increase the original project completion date.
A & c
資源平衡:
通過把項目資源時間降到最小來提高資源的有效使用:
典型的往往是對工序工期沒有影響
趨向于增加原項目的完成日期
A 和 c
5. The terms “planning” and “scheduling” are sometimes used interchangeably within a project; however, they are very different activities in a project. Which of following are scheduling activities?
The project will be completed by a team of international specialists, co-located in six countries, using workgroup tools available over the internet.
The vendor (s), for the widget component, must be selected by end of first quarter.
Due to the high cost and lengthy timeframes of producing components in-house, several of the components will be contracted out to vendors.
Vendor costs and delivery timeframes must be closely evaluated prior to contract ward.
b & d.
“計劃” 和“進度”兩個術語在項目中有時交替使用,然而它們在項目中是不同的行為. 下列那一個是進度活動?
項目由橫跨6個縣的國際專家組完成,他們可以在因特網(wǎng)上使用工作組的工具
對裝飾公司,賣主必須是最后的第一季度被挑選的
由于高成本和很寬的產(chǎn)品制造時間框架,許多公司就不同賣主簽約
賣主成本和交付時間框架必須同合同中要求的接近
b 和 d
6. Upon completing a project schedule, Roberta finds the critical path indicates the project will complete on April 15. as she works through the schedule, she finds there are several tasks with float. Task b has 10 days of free float, while task F has 5 days of total float. If the start of task B is delayed 15 days, what is the completion date of the project?
April 25
Not enough information provided to Calculate
April 20
April 10
在完成的項目進度上,Roberta 發(fā)現(xiàn)關鍵路徑顯示項目將在4月15日完成. 當她研究進度時,她發(fā)現(xiàn)有好多任務有工序移動. 任務B有10天的工序移動,而任務F有總共5天的工序移動. 如果B任務開始推遲15天,項目完成的日期是什么時候?
4月25
沒有足夠的信息計算
4月20
4月10
7. Working with the project team, the project manager found a way to fast track the project by starting Task D five days after task B has started, and working both tasks in parallel for 10 days. How will this affect the project?
The project will complete ten days sooner.
The critical path will change
The project will complete five days sooner
The duration on task “g” will be shortened.
B & c
在項目組的工作中,項目經(jīng)理發(fā)現(xiàn)了快速跟進的方法是在任務B開始5天后任務D開始,隨后同時進行10天. 它對項目有什么影響?
項目將早10天完成
關鍵路徑將改變
項目將早5天完成
任務G的工期將縮短5天
B 和 c
- 1武漢地鐵跨朱家河連續(xù)梁主墩混凝土澆筑完成
- 22015一級建造師《水利水電》知識點串講(20)
- 32015年咨詢工程師《工程項目組織與管理》每日一練(11.1)
- 4監(jiān)理:《建設工程合同管理》每日一練18
- 5濱海新區(qū)“十二五”末將建污水處理設施36座 規(guī)
- 6淮南2015年造價工程師考試5月24日至6月9日報名
- 72015咨詢工程師考試《工程項目組織與管理》試題(13)
- 8某大橋硫磺砂漿臨時支座施工
- 9煙臺市2015年安全工程師考試報名時間確定:4月29日至5月17日
- 102015項目管理與招標采購考點:服務項目管理實施
- 11北京違建4487萬平 違建當事人將進黑名單
- 12金溫鐵路潘橋大橋主體框架工程項目順利完工
- 13CR聚氨酯硬泡體屋面防水保溫工程施工工藝
- 14一級建造師復習資料:投標擔保與履約擔保
- 15湖南機械混凝土輸送泵控制措施做一些簡單的介紹
- 16項目管理與招標采購第四章:服務項目合同的執(zhí)行
- 17[四川]隧道工程施工組織設計(技術標)
- 182012一級建造師《市政工程》:盾構法施工的基本技術要點
- 19一級建造師考試精華總結:投標人的法律責任
- 20一級建造師管理與實務復習要點:孔道壓漿
- 21小高層項目工程管理責任范圍?
- 22深基坑土方護坡排水工程施工組織設計27P
- 232013年二級建造師《施工管理》每日一練(10.31)
- 24湖南:三湘大地涌動重點工程建設熱潮
- 252015年招標師考試《招標采購專業(yè)實務》習題精解七
- 262015年安全工程師《安全生產(chǎn)技術》每日一練(1.28-2.3)
- 272015年安全工程師相關法律知識練習(6)
- 282015年監(jiān)理工程師考試考場應試技巧
- 292015年咨詢工程師《工程咨詢概論》模擬題(八)
- 30[貴州]高原溶蝕構造丘陵區(qū)鐵路隧道實施性施工組織設計159頁(新奧法)
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓