2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十二
QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:
A A shortening of the critical path.
B A shortening of the noncritical path.
C A decrease in the total cost of the project.
D An increase in the cost of the project.
E A through D are possible based upon where the resources are deployed.
參考答案:E
QUEST Bar charts are most appropriate for:
A Comparing actual to planned performance to each activity.
B Showing slack time.
C Showing critical path dependencies.
D Showing which activities can be rearranged in parallel.
E All of the above.
參考答案:A
QUEST A non-critical path activity is completed in half the time. Then,
A The critical path is also reduced.
B The slack in the path containing this activity will increase.
C The total cost for this activity has decreased.
D Manpower from this activity can be assigned to other activities.
E All of the above.
參考答案:B
QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A Slack for each activity, critical path.
B Slack for each activity, high risk activities.
C Manpower shortages, high risk activities.
D High risk activities, non-critical paths.
E Manpower availability, contingency plans.
參考答案:A
QUEST ADM is an activity-on-arrow method. In this method, a dummy activity:
A Denotes a critical path relationship.
B Denotes any dependency relationship.
C Shows slack.
D Identifies customer deliverables dates.
E Identifies customer team meeting dates.
參考答案:B
相關(guān)試題:
2010年P(guān)MP美國項(xiàng)目管理考試習(xí)題及答案三十一
試題推薦:
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項(xiàng)目管理認(rèn)定考試全真模擬試題精選3
- 12015年咨詢工程師《項(xiàng)目決策分析與評(píng)價(jià)》每日一練(2.9)
- 2安全工程師輔導(dǎo)資料:防止輸電線路事故發(fā)生的注意事項(xiàng)
- 3安全工程師輔導(dǎo)資料:發(fā)電機(jī)組操作規(guī)程
- 42015一級(jí)建造師《水利水電》知識(shí)點(diǎn)串講(8)
- 52015年咨詢工程師《項(xiàng)目決策分析與評(píng)價(jià)》每日一練(4.16)
- 62015年監(jiān)理工程師考試答題技巧
- 7項(xiàng)目管理與招標(biāo)采購第五章:招標(biāo)采購風(fēng)險(xiǎn)管理的目標(biāo)
- 8中華人民共和國招標(biāo)投標(biāo)法 第二章 招標(biāo)
- 9濟(jì)南奧體中心設(shè)計(jì)與施工中的新技術(shù)
- 10某高速公路跨線橋施工安全技術(shù)措施及交通組織方案
- 11安全工程師考試《安全生產(chǎn)管理》第四講講義精選(1)
- 12招標(biāo)師歷年考試真題的意義
- 132015造價(jià)員復(fù)習(xí)資料:總價(jià)合同
- 14廈門2015年的招標(biāo)師培訓(xùn)
- 152015項(xiàng)目管理與招標(biāo)采購考點(diǎn):投融資服務(wù)項(xiàng)目合同管理
- 162015咨詢工程師考試《項(xiàng)目組織與管理》模擬練習(xí)(5)
- 17混凝土攪拌車防滑制動(dòng)系統(tǒng)故障診斷方法解析
- 18遼寧省2015年安全工程師考試報(bào)名時(shí)間為5月28日至6月25日
- 19整體電動(dòng)升降式外爬穿技術(shù)在高層建筑中的應(yīng)用
- 20造價(jià)工程師建設(shè)工程造價(jià)管理復(fù)習(xí)資料——造價(jià)工程師的權(quán)利
- 21監(jiān)理工程師應(yīng)組織相關(guān)人員寫出質(zhì)量處理報(bào)告,其主要內(nèi)容包括
- 22一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):合同
- 23徐州市2015年安全工程師考試報(bào)名時(shí)間確定:4月10日-30日
- 24安全工程師答疑精華:傳爆材料
- 25淺議建筑物沉降觀測點(diǎn)的布設(shè)
- 26招標(biāo)師相關(guān)考試經(jīng)驗(yàn)
- 27PMP項(xiàng)目管理:項(xiàng)目溝通管理練習(xí)題1
- 28信息系統(tǒng)項(xiàng)目管理師考試須知
- 292015年咨詢工程師知識(shí)點(diǎn):風(fēng)險(xiǎn)利用
- 302015造價(jià)員《安裝工程》基礎(chǔ)知識(shí)點(diǎn):熱塑性塑料
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓