QUEST A budget estimate should give the manager cost data accurate to within:
A -5 to +10 percent of actual cost
B -25 to +75 percent of actual cost
C -30 to +75 percent of actual cost
D -10 to +25 percent of actual cost
E None of the above
參考答案:D
QUEST The following types of costs are relevant to making a financial decision except:
A opportunity costs
B direct costs
C sunk cost
D unavoidable costs
E None of the above
參考答案:C
QUEST Which of the following types of cost are relevant to making financial decisions:
A sunk cost
B opportunity cost
C material cost
D A and C only
E B and C only
參考答案:E
QUEST In which of the following cost estimating techniques are statistics models used:
A nonparametric cost estimating
B parametric cost estimating
C life cycle cost estimating
D bottom-up estimating
E All of the above.
參考答案:B
QUEST Under the terms of 2/10 net 30, the buyer may:
A deduct 10% of the invoice amount for payment within 30 days
B deduct 2% of the invoice for payment within 10 days
C incurs a penalty on 10% for payments more than 30 days late
D settle the invoice with 2 equal payments; one within 10 days and the other within 30 days
E None of the above
參考答案:B