QUEST Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three most common escalation factors involve changes in:
A Overhead rates, labor rates and material costs.
B Overhead rates, schedule slippages, and rework.
C Rework, cost-of-living adjustments, and overtime.
D Material costs, shipping cost, and scope changes.
E Labor rates, material costs, and cost reporting.
參考答案:A
QUEST The three most common types of project cost estimates are:
A Order of magnitude, parametric, and budget.
B Parametric, definitive and top down.
C Order of magnitude, definitive and bottom up.
D Order of magnitude, budget and definitive.
E Analogy, parametric and top down.
參考答案:D
QUEST The work breakdown structure, the work packages, and the company's accounting system are tied together through the:
A Code of accounts.
B Overhead rates.
C Budgeting system.
D Capital budgeting process.
E All of the above.
參考答案:A
QUEST The profitability and technical data studies are provided in report format to owners and funders for acceptance. This type of report, used to solicit funding, is referred to as a(n) _____.
A Project feasibility study.
B Economic evaluation analysis.
C Risk management manual.
D Prospectus.
E None of the above
參考答案:D
QUEST The technique most commonly used to determine the profitability of a project includes _____ methods.
A Net present value (NPV).
B Return on investment (ROI).
C Discounted cash flow (DCF)
D Payout time and risk sensitivity analysis.
E All of the above.
參考答案:E
相關試題:
2010年PMP美國項目管理考試習題及答案五十五
試題推薦:
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3
- 12015年咨詢工程師《工程咨詢概論》每日一練3.24
- 2小竅門案例分析考場解題技巧
- 3攪拌車常規(guī)保養(yǎng)如何自行解決
- 4移動腳手架高空拼裝法施工鋼網(wǎng)架
- 5一級建造師建筑工程復習要點:制造成本
- 6鋼結構的防腐涂料與防火涂料
- 7安全工程師安全生產(chǎn)法復習資料——視同工傷
- 82015年招標師考試招標采購專業(yè)實務考前復習指導(50)
- 9造價員《安裝工程》考點:油漆、裱糊工程
- 10地下室基坑邊坡支護與土方開挖施工順序
- 11《項目管理與招標采購》輔導:工程建設項目風險管理概述
- 122015年咨詢工程師《項目決策分析與評價》每日一練(10.21)
- 132008注冊安全工程師考試輔導《安全生產(chǎn)管理知識》(五)
- 142015年咨詢工程師《工程項目組織與管理》每日一練(5.6)
- 15注冊消防工程師難嗎
- 16“北煤南運”通道蒙贛鐵路2013年開工
- 17大體積混凝土施工工藝標準
- 18招標師解析:招標采購的特點
- 19一級建造師法規(guī)及相關知識復習要點:索賠
- 20中交路橋中標G3012墨玉至和田高速公路工程
- 212015年監(jiān)理工程師《基本理論和相關法規(guī)》練習題(88)
- 222015年咨詢工程師《工程咨詢概論》考試模擬試題(1)
- 23什么是地震中的地聲現(xiàn)象
- 24項目管理與招標采購考試備考練習題精選(1)
- 25CAD模型在三坐標檢測及生產(chǎn)中的應用
- 26道路燈改造工程施工組織設計23p
- 27什么情況下水泥必須進行復試及水泥復試的項目有哪些
- 28薄壁空心墩首件施工基坑開挖要點
- 292015年監(jiān)理工程師應試指南——《理論與法規(guī)》
- 302015年咨詢工程師考試《咨詢概論》模擬試題(十七)
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓