1. the main player in project communication is the
a. sponsor
b. project manager
c. functional manager
d. functional team來源:考試大
e. all of the above.
ans: b
2. the type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that
project. for a firm fixed price contract, payment for risk _____ .
a. is accomplished by paying the actual costs to the contractor.
b. is accomplished by paying the contractor for his costs plus a fixed fee (profit).
c. is an undisclosed contingency in the contractor's bid.
d. is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
e. b and c
ans: c
3. which is not an element of procurement management?
a. purchasing
b. expenditure
c. marketing
d. inspection
e. b and d來源:考試大
ans: c
4. which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
a. 0.05
b. 0.1
c. 0.15
d. 0.25
e. 0.5
ans: d
5. bar charts are most appropriate for:
a. comparing actual to planned performance to each activity.
b. showing slack time.
c. showing critical path dependencies.
d. showing which activities can be rearranged in parallel.
e. all of the above.
ans: a
6. formal authority is often referred to as legitimate power. which two other forms of power are also considered to be legitimate power?
a. reward and penalty
b. reward and referent
c. referent and expert
d. expert and reward
e. penalty and referent
ans: a
7. power games, withholding information, and hidden agendas are examples of-.
a. noise
b. communication barriers
c. indirect communication
d. mixed messages
e. all of the above
ans: b
8. scope management is:來源:www.examda.com
a. a project control function.
b. employs change control.
c. a work authorization process.
d. considers cost, quality and schedule.
e. all of the above.
ans: e
9. the most common method for pricing out non-burdened labor hours for a three year project would be to:
a. price out the hours at the actual salary of the people to be assigned.
b. price out the work using a company-wide average labor rate.
c. price out the work using a functional group average labor rate.
d. all of the above.
e. a and b only.
ans: c
10. the principles of risk management should be followed only for:
a. complex projects
b. simple projects
c. large projects來源:考試大
d. a and c
e. all of the above.
ans: e
11. utility theory:
a. considers the risk propensity of the decision makers.
b. is based on proven statistical methods.
c. deals with the usefulness of the end product.
d. is a key element of iso 9000
e. b and c
ans: a
12. which is not part of the purchasing cycle?
a. defined need
b. transmit need
c. inspection
d. prepare and issue purchase order
e. a and d
ans: c
- 12015年二級建造師考試備考四步制勝法寶
- 2安全工程師考試《安全生產(chǎn)技術(shù)》模擬題(一)
- 32015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練7.4
- 4側(cè)石、平石及人行道施工
- 5山西:將再建兩座公路黃河大橋
- 6如果該項(xiàng)措施會對進(jìn)度目標(biāo)和質(zhì)量目標(biāo)產(chǎn)生不利影響
- 72013年二級建造師《建筑》:常見模板及其特性
- 8造價(jià)工程師土建計(jì)量復(fù)習(xí)要點(diǎn):鋼筋混凝土冷卻塔
- 92015年監(jiān)理工程師考試質(zhì)量、投資、進(jìn)度控制練習(xí)題(51)
- 102015年一級建造師考試《項(xiàng)目管理》精華知識點(diǎn)(7)
- 112015年安全工程師《事故案例分析》試題(14)
- 12高壓旋噴樁施工方法
- 13公路小橋涵軟土地基加固處理
- 142015造價(jià)工程師《理論與法規(guī)》輔導(dǎo)講義(6)
- 15餐飲城商住現(xiàn)場消防施工方案
- 162015年咨詢工程師《項(xiàng)目決策分析與評價(jià)》每日一練(3.25)
- 17“三材”節(jié)約率中的“三材”是什么意思?
- 18煤層底板含水層注漿改造技術(shù)在焦作礦區(qū)的應(yīng)用(二)
- 19冬季施工方法
- 20安全工程師相關(guān)法律知識點(diǎn):保障從業(yè)人員的安全生產(chǎn)權(quán)
- 212015年安全工程師考試《安全法及相關(guān)知識》習(xí)題21
- 22造價(jià)工程師技術(shù)與計(jì)量(土建)復(fù)習(xí)資料——巖溶與土洞
- 23巖石的成因類型
- 242015年安全工程師《安全生產(chǎn)法及法律知識》鞏固練習(xí)(5)
- 25陜西省發(fā)文嚴(yán)格控制水泥等大氣污染行業(yè)
- 26山西:11月全省重點(diǎn)工程建設(shè)保持良好態(tài)勢
- 272015年二級建造師《法規(guī)》重點(diǎn):知識產(chǎn)權(quán)的特征
- 282012年一級建造師輔導(dǎo)資料:工程項(xiàng)目內(nèi)部會計(jì)控制
- 29注冊咨詢工程師2015年考試《經(jīng)濟(jì)政策》習(xí)題(6)
- 302015年咨詢工程師《項(xiàng)目決策分析與評價(jià)》每日一練(12.2)
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓