QUEST We assign human and non-human resources in the _____ phase of the budget.
A conceptual
B planning
C development
D implementation
E close-out
參考答案:D
QUEST Project trade-offs vary between
A risk, cost and schedule.
B direct cost, indirect cost, and resource availability
C quality, schedule and time
D cost, quality and schedule
E contract terms, scope and budget
參考答案:D
QUEST The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
A budget, schedule
B quality requirements, schedule
C size, type of industry
D nature, size
E project manager, sponsor
參考答案:D
QUEST The time necessary to complete a project is called the _______ of a project.
A Implementation Time
B Life Cycle
C Operation Time
D Critical Path
E Completion Phase
參考答案:B
QUEST When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
參考答案:E
試題推薦:
2010年P(guān)MP美國項目管理考試習題及答案一
2010年P(guān)MP美國項目管理考試習題及答案二
2010年P(guān)MP美國項目管理考試習題及答案三
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3