QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ . 
A Project specification tree. 
B Customer's deliverable list. 
C Customer's milestone dates. 
D Work breakdown structure. 
E Listing of customer team meeting dates. 
參考答案:D

QUEST The critical path in a network is the path that: 
A Has the greatest degree of risk. 
B Will elongate the project if the activities on this path take longer than anticipated. 
C Must be completed before all other paths. 
D All of the above. 
E A and B only. 
參考答案:B

QUEST The major difference between PERT and CPM networks is: 
A PERT requires three time estimates whereas CPM requires one time estimate. 
B PERT is used for construction projects whereas CPM is used for R & D. 
C PERT addresses only time whereas CPM also includes cost and resource availability. 
D PERT requires computer solutions whereas CPM is a manual technique. 
E PERT is measured in days whereas CPM uses weeks or months. 
參考答案:A

QUEST A calendar that identifies when a project may be performed on an activity is called a: 
A Project calendar. 
B Resource calendar. 
C Milestone point. 
D Key point. 
E Work unit. 
參考答案:A

QUEST Planning activities such that predetermined resource availability pools are not exceeded is called: 
A Resource leveling. 
B Manpower leveling. 
C Resource limited planning. 
D Manpower planning. 
E Manpower contingency planning. 
參考答案:C

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習(xí)題及答案三十二

試題推薦:

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:55    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件