2010年PMP美國項目管理考試習題及答案28

申請免費試用、咨詢電話:400-8352-114

QUEST Which is not one of the five classifications of work found in a purchasing operafion? 
A Management 
B Buying 
C Follow-up and expediting 
D Marketing 
E Clerical 
參考答案:D

QUEST _____ is based on information gathered and analyzed about demand and supply.  This forecast provides a prediction of short and long term prices and the underlying reasons for those trends. 
A Demand forecast 
B Price forecast 
C Supply forecast 
D Production forecast 
E None of the above. 
參考答案:B

QUEST Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the: 
A Buyer 
B Third party 
C Contractor 
D All of the above 
E None of the above 
參考答案:C

QUEST The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure. 
A Performance 
B Functional 
C Technical 
D Base Line 
E None of the above. 
參考答案:A

QUEST There are four methods of government procurement.  Which is not one of these methods? 
A Assistance 
B Sealed bidding 
C Competitive proposals 
D Acquisition 
E Small purchases 
參考答案:D

相關試題:

2010年PMP美國項目管理考試習題及答案27

試題推薦:

2010年PMP美國項目管理認定考試全真模擬試題精選1

2010年PMP美國項目管理認定考試全真模擬試題精選2

2010年PMP美國項目管理認定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:53    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]
相關文章:

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件