來源:考試大網(wǎng)1. the highest degrees of project risk and uncertainty are associated with the following phase of the project:
a. conceptual
b. execution
c. cut-over來源:www.examda.com
d. post project evaluation
e. a and d only
ans: a
2. the most common types of schedules are gantt charts, milestone charts, line of balance, and:
a. networks.
b. time phased events.
c. calendar integrated activities.
d. a and c only.
e. b and c only.
ans: a
3. which of the following is often overlooked in achieving effective communication?
a. speaking clearly
b. listening
c. interpreting
d. maintaining eye contact
e. manipulating the conversation
ans: b
4. which type of contract requires that the buyer keep the tightest labor/material cost control?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee考試大論壇
d. firm fixed price
e. firm fixed price plus incentive
ans: b
5. a task-oriented family tree of activities is a:
a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
ans: c
6. adding 5 people to a 4 person team increases the communication channels by a factor of:
a. 2 times
b. 3 times
c. 4 times來源:考試大
d. 5 times
e. 6 times
ans: e
7. cost management includes:
a. cost estimating/forecasting.
b. cost budgeting/cost control.
c. cost applications.
d. all of the above.
e. a and b only.
ans: d
8. participative management:
a. involves the solicitation of information from all team members.
b. assumes that members avoid work and responsibility.
c. suggests the sharing of power and decision making.
d. employs a theory x style of leadership.
e. a and c
ans: e
9. the auditing function that provides feedback about the quality of output is referred to as:
a. quality control.
b. quality planning.
c. quality assurance.
d. quality improvement
e. all of the above.
ans: c
10. the lowest dollar amount 'at stake' is associated with the following phase of the project:
a. conceptual
b. execution來源:www.examda.com
c. cut-over
d. post project evaluation
e. a and d only
ans: a
11. the major disadvantage of a bar chart is:
a. lack of time-phasing.
b. cannot be related to calendar dates.
c. does not show activity interrelationships.
d. cannot be related to manpower planning.
e. cannot be related to cost estimates.
ans: c
12. which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee
d. firm fixed pricewww.Examda.CoM
e. firm fixed price plus incentive
ans: e
- 1咨詢工程師2015《項(xiàng)目組織與管理》練習(xí)題(10)
- 2全國(guó)監(jiān)理工程師臨考密押試卷《建設(shè)工程合同管理》(一)
- 3某大廈施工現(xiàn)場(chǎng)平面布置圖
- 4綜合單價(jià)是指全費(fèi)用綜合單價(jià)還是綜合單價(jià)
- 5泥質(zhì)防滲層施工控制要求
- 6建設(shè)工程目標(biāo)控制的措施典型題解(一)
- 72015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練5.20
- 8旅游公路改擴(kuò)建工程綠化與景觀工工程施工組織設(shè)計(jì)方案
- 9移動(dòng)模架和懸臂澆注中預(yù)應(yīng)力筋是不是連續(xù)的?
- 10煤層瓦斯的回收利用
- 11[臨沂市]06年安全工程師考試報(bào)名通知
- 12高能燃燒劑爆破法
- 132015年注冊(cè)安全工程師事故案例分析模擬試題(二十五)
- 14安全工程師案例分析復(fù)習(xí)要點(diǎn):制氫系統(tǒng)
- 152015年安全工程師生產(chǎn)案例模擬練習(xí)(14)
- 162015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練2.7
- 17市政管理與實(shí)務(wù)知識(shí):橋梁工程鉆孔灌注樁施工安全措施
- 182015年咨詢工程師《工程咨詢概論》練習(xí)題15
- 19水利部發(fā)布兩條實(shí)施細(xì)則 鼓勵(lì)民資參與水利工程
- 20[天津]2008年度注冊(cè)安全工程師執(zhí)業(yè)資格考試5月22-26日?qǐng)?bào)名
- 21一級(jí)建造師管理與實(shí)務(wù)復(fù)習(xí)要點(diǎn):時(shí)限
- 22《項(xiàng)目決策分析與評(píng)價(jià)》知識(shí)點(diǎn):企業(yè)投資項(xiàng)目決策(核準(zhǔn))程序
- 23小專題:2015年二級(jí)建造師考試報(bào)名條件、報(bào)名時(shí)間解讀
- 242015咨詢工程師《項(xiàng)目決策分析與評(píng)價(jià)》模擬題(12)
- 252015年安全工程師《安全生產(chǎn)管理知識(shí)》精華習(xí)題(82)
- 262015年造價(jià)員基礎(chǔ)知識(shí)重點(diǎn)輔導(dǎo):新增資產(chǎn)
- 272015年凱里市造價(jià)工程師考試用書
- 28全國(guó)咨詢工程師2015年《項(xiàng)目決策分析與評(píng)價(jià)》習(xí)題(8)
- 292015年咨詢工程師《工程項(xiàng)目組織與管理》每日一練(5.20)
- 30安全工程師生產(chǎn)法復(fù)習(xí)資料——重新評(píng)價(jià)
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓