1 Historical records during close-out are useful to _____ and _____ for future projects.
A Predict trends, highlight problems.
B Analyze successes, shortfalls.
C Analyze strengths, document results.
D Support litigation, defend claims.
E Justify results, set standards.
ans:A
2 A clear definition of the user's needs serves as the direct basis for the:
A Work breakdown structure.
B Functional requirements.
C Project cost estimate. 來(lái)源:www.examda.com
D Selection of personnel.
E Termination decision.
ans:B
3 Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?
A Project.
B Strong matrix.
C Weak matrix.
D Project coordinator. 來(lái)源:www.examda.com
E Project expeditor.
ans:C
4 The project charter:
A Expresses upper management commitment to the project.
B Provides that authority by which the project will be run.
C Establishes that organizational structure with the project.
D Specifies overall objectives and timeframe of the project.
E All of the above.
ans:E
5 The WBS is:
A An organization oriented family tree of the project.
B A task oriented family tree of the project.
C A cost centered structure of the project.
D Only required on large complex projects where separately identifiable work packages are difficult to construct.
E None of the above. 來(lái)源:考試大
ans:B
6 Including the customer in the process of project planning is:
A Slow and counterproductive.
B Essential in the definition and documentation of project goals.
C Necessary, but of limited value.
D Unnecessary because project goals are defined in the proposal stage.
E None of the above.
ans:B
7 The scope management provides:
A A basis for future decisions about the project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above.
E B and C only. 考試大論壇
ans:D
8 During project execution, a line manager informs you that he will not have sufficient resources available next month to support your and two other projects. The best way to handle this problem would be to:
A Ask the line manager to make the decision.
B Ask the line manager to work with senior management to prioritize the work.
C Ask your sponsor to meet with the line manager.
D Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.
E Prepare a purchase order to outsource the work.
ans:D
9 Proper implementation of project management will guarantee that:
A Budgets will be met.
B Schedules will be adhered to.
C Quality/performance will be met.
D The project will be a success. 考試大(www.Examda。com)
E None of the above.
ans:E
10 The most difficult decision for the executive sponsors to make at the end-of-phase review meeting is:
A Budget allocations for the next phase.
B Authorizing scope changes for the next phase.
C Authorizing budget increases for the next phase based upon scope changes.
D Canceling the project.
E All of the above.
ans:D
11 The financial closeout of a project dictates that:
A All project funds have been spent.
B No charge numbers have been overrun.
C No follow-on work from this client is possible.
D No further charges can be made against the project.
E All of the above.
ans:D
12 A project can best be defined as:
A Series of non-related activities designed to accomplish single and multiple objectives.
B Coordinated effort of related activities designed to accomplish a goal without a well-established end point.
C Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.
D Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.
E All of the above.
ans:D
- 1某高速公路透層、下封層施工指導(dǎo)意見(jiàn)
- 2回填片石施工方法
- 32015年造價(jià)員考試重點(diǎn)混泥土養(yǎng)護(hù)
- 42015年監(jiān)理工程師《基本理論和相關(guān)法規(guī)》練習(xí)題(38)
- 5淺析生產(chǎn)生活中的荷載
- 6薄抹灰EPS保溫板外墻保溫施工工藝(PPT)
- 72015年安全工程師考試《安全生產(chǎn)技術(shù)》練習(xí)試題(15)
- 8工藝管道、閥門(mén)基礎(chǔ)知識(shí)培訓(xùn) 86p
- 908安全工程師《生產(chǎn)法及相關(guān)法律知識(shí)》模擬試題(六)
- 10浙江省2015年安全工程師報(bào)名時(shí)間為4月13日至27日
- 11園林綠化施工通用表格
- 12XYPEX(賽柏斯)防水施工工藝
- 13地下連續(xù)墻有哪些缺點(diǎn) ?
- 142015造價(jià)員《土建工程》知識(shí)點(diǎn):其他墻體
- 152015年咨詢工程師《項(xiàng)目決策分析與評(píng)價(jià)》每日一練(12.30)
- 16一級(jí)建造師工程經(jīng)濟(jì)復(fù)習(xí)要點(diǎn):設(shè)備購(gòu)置
- 172015年咨詢工程師《工程咨詢概論》考試模擬題(11)
- 18安全工程師相關(guān)法律知識(shí)復(fù)習(xí)要點(diǎn):“三定”方案
- 19某山莊公園規(guī)劃文本
- 20三條高速路估算總投資316億
- 21混凝土輸送泵的閘板閥在使用過(guò)程中應(yīng)注意的幾點(diǎn)
- 22項(xiàng)目進(jìn)度管理體系
- 232015年安全工程師考試《安全生產(chǎn)技術(shù)》資料:模板工程
- 242015年注冊(cè)監(jiān)理工程師《理論法規(guī)》習(xí)題(7)
- 25氮?dú)庠诿旱V防滅火中的應(yīng)用
- 26一級(jí)建造師實(shí)務(wù)復(fù)習(xí)要點(diǎn):一定規(guī)模危險(xiǎn)性較大工程
- 27招標(biāo)師考試:物流服務(wù)項(xiàng)目管理
- 28項(xiàng)目信息化管理研究
- 292015年咨詢工程師《宏觀經(jīng)濟(jì)政策》練習(xí)題(2)
- 30造價(jià)工程師技術(shù)與計(jì)量復(fù)習(xí)要點(diǎn):山東03定額,復(fù)合木模板問(wèn)題
成都公司:成都市成華區(qū)建設(shè)南路160號(hào)1層9號(hào)
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓