PMP認證考試練習題及參考答案(四十四)
A Confrontation
B Compromise
C Smoothing
D Forcing 來源:www.examda.com
E Withdrawal
ans:A
2 Formal authority is often referred to as legitimate power. Which two other forms of power are also considered to be legitimate power?
A Reward and penalty
B Reward and referent
C Referent and expert
D Expert and reward
E Penalty and referent
ans:A
3 In the past, most project managers have come from _____ fields without proper _____ training or education in skills
A Technical; accounting/finance
B Technical; management
C Technical; psychological
D Marketing; technology-oriented
E Business; manufacturing know-how
ans:B
4 Project managers need exceptionally good communication and negotiation skills primarily because:
A They may be leading a team over which they have no direct control
B Procurement activities mandate this
C They are expected to be technical experts 來源:www.examda.com
D They must provide executive/customer/sponsor briefings
E All of the above
ans:A
5 The major difference between project and line management is that the project manager may not have any control over which basic management function?
A Decision-making
B Staffing
C Rewarding
D Tracking/monitoring
E Reviewing
ans:B
6 A good team leader must be concerned not only with _____ but also with _____ .
A Long term goals; short term goals
B Organizational goals; personal goals
C Legitimate power; referent power
D Group efficiency; power and authority
E Tasks to be accomplished; needs of the team members
ans:E
7 In small companies, project managers and line managers are:
A Never the same person
B Always the same person
C Sometimes the same person
D Always in disagreement with each other
E Forced to act as their own sponsors
ans:C
8 A project manager who allows the team to make the majority of the decisions is demonstrating a(n) ____ leadership style.
A Laissez-faire
B Boss-centered
C Subordinate centered
D Autocratic
E Demographic
ans:C
9 R & D project managers in high-tech companies most often motivate using _____ power.
A Expert
B Reward
C Referent
D Identification 來源:考試大
E None of the above
ans:A
10 Charisma would be an example of _____ power.
A Legitimate
B Reward
C Coercive
D Expert
E Referent
ans:E
11 Which of the following types of power comes through the organizational hierarchy
A Coercive
B Reward
C Referent
D Legitimate
E Expert
ans:D
12 An example of coercive power would be:
A Demotion
B Reduction in wages
C Disciplinary layoff
D Reprimand
E All of the above
ans:E
- 12015年注冊安全工程師事故案例分析模擬試題(十四)
- 22015年招標師:招標采購實務(wù)模擬試題14
- 3聚乙烯丙綸復(fù)合防水卷材施工工藝
- 4項目管理與招標采購第二章:建設(shè)工程項目履行合同的擔保形式
- 5安全工程師考試《法律法規(guī)》習題班講義精選(50)
- 62015招標師考試:招標采購專業(yè)實務(wù)詳解(第三章)匯總
- 7安全工程師《生產(chǎn)管理》自測題(26)
- 82015年咨詢工程師《項目決策分析與評價》每日一練12.19
- 92015年監(jiān)理工程師《建設(shè)工程合同管理》練習題(83)
- 102015年安全工程師《管理知識》資料:民事責任
- 112015年咨詢工程師《工程咨詢概論》考試模擬試題(9)
- 122015年咨詢工程師《宏觀經(jīng)濟政策》練習題(46)
- 132015年招標師:招標采購實務(wù)模擬試題20
- 14涓夌淮鏂藉伐鐜板満騫抽潰璁捐?搴旂敤
- 152015招標師考試順利開考(圖文報道)
- 162015年安全工程師生產(chǎn)管理知識模擬精選(11)
- 17IPMP面試必讀:評估師
- 18巖土工程師答題技巧
- 19深化設(shè)計管理
- 20工程監(jiān)理單位應(yīng)遵守的基本原則之一是什么
- 21項目投標合同文本制定 內(nèi)容
- 22竹網(wǎng)—土工布處治軟基
- 23某大橋承臺大體積砼的施工
- 24全站儀在工程變形監(jiān)測中的應(yīng)用
- 252015年白山造價工程師報名時間
- 26土釘墻在邊坡加固防護中的應(yīng)用
- 272015年咨詢工程師《工程項目組織與管理》每日一練12.15
- 282015年二級建造師《法規(guī)及相關(guān)知識》每日一練(6.21)
- 292015年安全工程師考試《管理知識》:安全評價業(yè)務(wù)分類
- 302011年P(guān)MP考試試題分布更新通知
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓