當(dāng)前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
PMP認(rèn)證考試練習(xí)題及參考答案(五十二)
A The development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments.
B the development of schedule alternatives and work-around
C the management of a contingency budget
D an assessment of project shut-down liabilities.
E A and C
ans:A
2 During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
ans:A 考試大(www.Examda。com)
3 Budgeted contingencies can be detemined by:
A past experience
B applying standard allowances
C detemining the sum total of the most probable variances of the various risk items properly identified.
D All of the above.
E None of the above.
ans:D
4 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:
A Work breakdown structure
B milestone review and schedule technique
C cost/schedule control system
D planning programming budget system
E program and evaluation review technique
ans:A
5 Many companies self insure against some risk. Problems which can arise from self-insurance include:
A failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial damage to the company
B stiff competition from insurance companies
C confusion of business risks with insurable risks.
D A and C
E All of the above.
ans:D
6 Sensitivity analysis can be used in risk analysis to:
A Substitute for uncertainty analysis in risk quantification
B estimate the level of risk aversion adopted by management
C estimate the effect of change of one project variable on the overall project
D A and B
E All of the above.
ans:C
7 Risk event probability is defined as:
A the total number of possible events divided into the expectations or frequency of the risk event
B the number of times the risk event may occur
C the fraction of the total project tasks which may be affected by the risk event
D the total number of possible events divided into the consequences of the risk event.
E A and B
ans:A
8 In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.
ans:E
9 Total Project Risk:
A should not be calculated for small projects
B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D A and B
E A and C 考試大論壇
ans:C
10 Risk mitigation involves all but which of the following:
A developing system standards (policies, procedure, responsibility standards)
B obtaining insurance against loss
C identification of project risks
D performing contingent planning
E developing planning alternatives
ans:C
11 The principles of risk management should be followed only for:
A complex projects
B simple projects
C large projects
D A and C
E All of the above.
ans:E
12 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .
A Is accomplished by paying the actual costs to the contractor.
B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C Is an undisclosed contingency in the contractor's bid.
D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E B and C
ans:C
- 12015年二級建造師考試《十大題型解讀》
- 22015年招標(biāo)師:招標(biāo)采購專業(yè)實務(wù)精選習(xí)題38
- 32015招標(biāo)師考試:招標(biāo)采購專業(yè)實務(wù)第八章詳解11
- 4逐字逐句讀課本 考試大綱扣緊點
- 52012年pmp模擬試題及答案(二)
- 62015年造價員基礎(chǔ)知識:控制電纜
- 7[滿洲里]06造價工程師資格考試報名
- 8工程造價知識:建設(shè)工程總承包合同管理
- 92013年二級建造師《法規(guī)及相關(guān)知識》每日一練(2.3)
- 102015招標(biāo)師考試教材《法規(guī)與政策》:第五章2
- 112015年咨詢工程師《分析與評價》每日一練(2.27)
- 12土方工程的分類及特點是什么?
- 13一級建造師法規(guī)及相關(guān)知識復(fù)習(xí)要點:標(biāo)的物毀損滅失風(fēng)險
- 14建設(shè)工程竣工規(guī)劃驗收測量面積計算的探討
- 15安徽五河住房城鄉(xiāng)建設(shè)局為美好鄉(xiāng)村規(guī)劃把脈
- 162015年咨詢工程師每日一練免費在線測試(2015.10.31)
- 17工程機械市場平衡效應(yīng)
- 182015年咨詢工程師《宏觀經(jīng)濟(jì)政策與發(fā)展規(guī)劃》輔導(dǎo)正式開課啦
- 19全球最大發(fā)電站前20位榜單揭曉
- 20風(fēng)景園林知識要點
- 21二級建造師法規(guī)知識點:合同的承諾
- 222015年招標(biāo)師《案例分析》:委托人與代理人權(quán)利義務(wù)
- 23影響混凝土輸送泵正常發(fā)揮的因素
- 242015年監(jiān)理工程師《建設(shè)工程三大控制》練習(xí)題(15)
- 252015一級建造師《水利水電工程管理與實務(wù)》講義(13)
- 26沖鉆孔灌注樁施工材料的質(zhì)檢控制
- 272015年招標(biāo)師招標(biāo)采購專業(yè)實務(wù)重點解析8
- 282015造價員《安裝工程》知識:建設(shè)工程造價專業(yè)人員資格管理
- 292015年安全工程師《安全生產(chǎn)管理知識》精華習(xí)題(36)
- 302015年度造價工程師執(zhí)業(yè)資格考試報名匯總(更新中…)
成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓