項(xiàng)目管理師考前模擬試題(二)及參考答案

申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114

Disclaimer: These questions are intended for study purposes only. Success on these questions is not indicative of success on the Project Management Professional Certification Examination. This download of the Sample Exam Questions is for your personal use and NOT FOR commercial use. Any unauthorized use or duplication of this document is prohibited!

   1. Activity duration estimate inputs include all of the following except:

   A. Resource requirements.
   B. Basis of estimates.
   C. Activity lists.
   D. Constraints.
   2. All of the following are contract types except:

   A. Unit-price.
   B. Make-or-buy.
   C. Cost reimbursable.
   D. Lump sum.
   3. Initiation inputs for a project include all of the following except:

   A. Product description.
   B. Strategic plan.
   C. Project charter.
   D. Selection criteria.
   4. Responses to risk threats include all of the following except:

   A. Avoidance.
   B. Acceptance.
   C. Mitigation.
   D. Rejection.
   5. The process of performance reporting includes all of the following except _____________.

   A. Status reporting.
   B. Progress reporting.
   C. Forecasting.
   D. Product analysis
   6. Constrained optimization methods of project selection include:

   A. Scoring models.
   B. Benefit-cost ratios.
   C. Multi-objective programming algorithms.
   D. Subjective analyses.
   7. Which of the following statements concerning contract type is correct?

   A. A fixed price contract contains the most risk for the buyer.
   B. Cost reimbursable contracts offer sellers the highest profit potential.
   C. Lump sum contracts offer sellers the greatest profit potential.
   D. Unit price contracts are illegal in many jurisdictions.
   8. A Work Breakdown Structure (WBS) numbering system should allow project staff to:

   A. Identify the level at which individual WBS elements are found.
   B. Identify configuration management milestones.
   C. Estimate the costs of WBS elements.
   D. Provide project justification.

   9. All of the following are true quality statements except:

   A. Quality improvement depends upon better definition and increased awareness of the
requirements/specifications.
   B. Project quality management must address both management of the project and the product of the project.
   C. Recognition of key actions required of each team member is necessary to meet quality objectives.
   D. Computer-aided design systems can improve quality, but only at the expense of an increase in the cost of design.
   10. All of the following are examples of tools often used in cost estimating except:

   A. Parametric modeling.
   B. Analogous estimating.
   C. Bottom-up estimating.
   D. Activity duration estimates.
 11. At XYZ Inc., the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30% of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the loaded” hourly wage for a semi-skilled worker at XYZ Inc.? 

   A. $27.14. 
   B. $28.96. 
   C. $30.03. 
   D. $29.12. 
   12. Of the following estimates, which most accurately reflect the actual cost of the project? 

   A. Conceptual estimates. 
   B. Order of magnitude estimates. 
   C. Preliminary estimates. 
   D. Bottom-up estimates. 
   13. The most crucial time for project risk assessment is: 

   A. When a problem surfaces. 
   B. During the planning phase. 
   C. During the close-out phase. 
   D. After the project schedule has been published. 
   14. When there is uncertainty associated with one or more aspects of the project, one of the first steps to take is to: 

   A. Revise project plan. 
   B. Conduct a risk-benefit analysis. 
   C. Conduct a needs analysis. 
   D. Increase the estimated cost of the project. 
   15. Including a contingency reserve in the project budget is intended to: 

   A. Reduce the probability of scope changes. 
   B. Increase the probability of scope changes. 
   C. Reduce the probability of a cost overrun. 
   D. Increase the probability of a cost overrun. 
   16. Given the information in the following table, what is the expected value from this risk event? Probability Result 

    A. -10,000. 
   B. - 7,500. 
   C. + 2,500. 
   D. -7,000. 
   17. A contractor is working on a fixed price contract that calls for a single, lump sum payment upon satisfactory completion of the contract. About halfway through the contract, the contractor project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors. The contractor asks for a partial payment for work accomplished. Which of the following actions by the buyer is most likely to cause problems for the project? A. Starting partial payments for work accomplished. 
   B. Making no payments because it would violate the conditions of the contract. 
   C. Paying for work accomplished to date. 
   D. Negotiating a change to the payment conditions in the contract. 
   18. A precise description of a physical item, procedure, or service for implementation of an item or service is called : 

   A. Work package. 
   B. Baseline. 
   C. Product description. 
   D. Work breakdown structure (WBS) element. 
   19. A project should be terminated for all of the following reasons except: 

   A. Lack of team synergy. 
   B. The project no longer meets the company’s objectives. 
   C. The resources are not available to complete project activities. 
   D. Project funding has been significantly reduced. 
   20. One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and: 

   A. Divide it by the schedule performance index. 
   B. Multiply it by the schedule performance index. 
   C. Multiply it by the cost performance. 
   D. Divide it by the cost performance index. 


   參考答案: 
   1.B 2.B 3.C 4.D 5.D 6.C 7.C 8.A 9.D 10.D 11.D 12.D 13.B 14.B 15.C 16.D 17.B 18.C 19.A 20.D 
發(fā)布:2007-03-02 10:12    編輯:泛普軟件 · xiaona    [打印此頁(yè)]    [關(guān)閉]