QUEST Using the situation stated in the Special window,  what is the cost variance for Case #9? 
A ¥-1,000 
B ¥1,000 
C -2000 
D 2000 
E 0 
參考答案:B

QUEST Using the situation stated in the Special window,  what is present value of $1000 at 12% at the end of 5 years? 
A ¥3,605.00 
B ¥0.57 
C ¥567.00 
D ¥892.86 
E ¥3.61 
參考答案:C

QUEST Using the situation stated in the Special window,  what is net present value of an annual income flow of $1600 at 14% over the next three years? 
A ¥3,713.60 
B ¥0.68 
C ¥1,080.00 
D ¥476.19 
E ¥2.32 
參考答案:A

QUEST Using the situation stated in the Special window,  what is the labor rate cost variance? 
A ¥5,500.00 
B ¥1,500.00 
C ¥-100.00 
D ¥-0.10 
E ¥5,600.00 
參考答案:D

QUEST Using the situation stated in the Special window,  what is the total price variance for direct material? 
A ¥140.00 
B ¥736.00 
C ¥0.02 
D ¥-350.00 
E ¥5,850.00 
參考答案:B

相關(guān)試題:

2010年P(guān)MP美國項目管理考試習(xí)題及答案四十二

試題推薦:

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2

2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3

發(fā)布:2007-03-02 10:54    編輯:泛普軟件 · xiaona    [打印此頁]    [關(guān)閉]
相關(guān)文章:

泛普軟件項目管理工具其他應(yīng)用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統(tǒng) 項目管理系統(tǒng) 施工管理軟件 建筑工程項目管理軟件 工程管理軟件