PMP認證考試練習題及參考答案(二十三)

申請免費試用、咨詢電話:400-8352-114

1 Work packages are used to:
A Represent units of work at a level where work is performed.
B Clearly distinguish one work package from all others assigned to a single functional group.
C Limit the work to be performed to relatively short periods of time.
D All of the above. 考試大論壇
E A and B only
ans:D
2 Project life cycles are very useful for _____ and _____ .
A Configuration management, termination
B Objective setting, information gathering
C Standardization, control
D Configuration management, weekly status updates
E Approval, termination
ans:C
3 Which of the following are included as part of a scope statement?
A Project justification
B Project deliverables
C Project objectives
D All of the above
E B and C
ans:D
4 The initial document that formally recognizes the existence of a project is the _____ .
A Scope baseline
B Management plan 來源:www.examda.com
C Project charter
D Configuration control report
E None of the above
ans:C
5 Which of the following is not a scope management process?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
ans:D
6 In which of the following scope management processes is the scope management plan prepared?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
ans:B
7 The project charter is prepared in which scope management process?
A Initiation
B Scope planning 考試大論壇
C Scope Definition
D Scope change control
E Scope verification
ans:A
8 The work breakdown structure (WBS) is first developed in which scope management process?
A Initiation
B Scope planning
C Scope change control
D Scope Definition
E Scope verification
ans:D
9 In which of the following scope management processes are subject matter experts used?
A Initiation
B Scope planning 來源:www.examda.com
C Scope Definition
D Scope change control
E Scope verification
ans:A
10 A Work Berakdown Structure is most useful for:
A Identifying individual tasks for a project.
B Scheduling the start of tasks.
C Developing a cost estimate.
D Determining potential delays.
E A and C.
ans:E
11 The scope statement provides
A A basis for future decisions about a project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above
E B and C only
ans:D
12 A work breakdown structure:
A assures all work is identified.
B subdivides the project into manageable segments.
C provides the project sponsor with a time-phase task summary.
D both A and B.
E All of the above.
ans:D

發(fā)布:2007-03-02 10:51    編輯:泛普軟件 · xiaona    [打印此頁]    [關閉]