2012年pmp考試模擬試題及答案(五)
QUEST A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
A 4 weeks
B 5 weeks
C 6 weeks
D 7 weeks
E None of the above.
B
QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
A All activities.
B Only those activities with the longest time durations.
C Those activities on the critical path begining with the longest time duration activities.
D Those activities with the greatest degree of risk.
E None of the above.
C
QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:
A A shortening of the critical path.
B A shortening of the noncritical path.
C A decrease in the total cost of the project.
D An increase in the cost of the project.
E A through D are possible based upon where the resources are deployed.
E
QUEST Bar charts are most appropriate for:
A Comparing actual to planned performance to each activity.
B Showing slack time.
C Showing critical path dependencies.
D Showing which activities can be rearranged in parallel.
E All of the above.
A
QUEST A non-critical path activity is completed in half the time. Then,
A The critical path is also reduced.
B The slack in the path containing this activity will increase.
C The total cost for this activity has decreased.
D Manpower from this activity can be assigned to other activities.
E All of the above.
B
QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A Slack for each activity, critical path.
B Slack for each activity, high risk activities.
C Manpower shortages, high risk activities.
D High risk activities, non-critical paths.
E Manpower availability, contingency plans.
A
QUEST ADM is an activity-on-arrow method. In this method, a dummy activity:
A Denotes a critical path relationship.
B Denotes any dependency relationship.
C Shows slack.
D Identifies customer deliverables dates.
E Identifies customer team meeting dates.
B
QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ .
A Project specification tree.
B Customer's deliverable list.
C Customer's milestone dates.
D Work breakdown structure.
E Listing of customer team meeting dates.
D
QUEST The critical path in a network is the path that:
A Has the greatest degree of risk.
B Will elongate the project if the activities on this path take longer than anticipated.
C Must be completed before all other paths.
D All of the above.
E A and B only.
B
QUEST The major difference between PERT and CPM networks is:
A PERT requires three time estimates whereas CPM requires one time estimate.
B PERT is used for construction projects whereas CPM is used for R & D.
C PERT addresses only time whereas CPM also includes cost and resource availability.
D PERT requires computer solutions whereas CPM is a manual technique.
E PERT is measured in days whereas CPM uses weeks or months.
A
QUEST A calendar that identifies when a project may be performed on an activity is called a:
A Project calendar.
B Resource calendar.
C Milestone point.
D Key point.
E Work unit.
A
QUEST Planning activities such that predetermined resource availability pools are not exceeded is called:
A Resource leveling.
B Manpower leveling.
C Resource limited planning.
D Manpower planning.
E Manpower contingency planning.
C
QUEST A comparison of completion status to baseline is referred to as _____.
A Earned value measurement.
B Percent complete.
C ACWP.
D BCWS
E None of above.
A
QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:
A Slack
B Free float.
C Restricted float.
D Level float.
E Lag
E
QUEST Overlapping activities on a project, such as design and construction, is referred to as:
A Fast tracking
B Risk conversion.
C Parallel management.
D Process improvement.
E Synchronous manufacturing
A
QUEST A computer tape which contains historical project information is called ____ tape.
A Database
B Baseline.
C Archive.
D Lessons learned.
E Life cycle summary.
C
QUEST Which method shown below is acceptable for reducing cost or shortening the schedule?
A "Crashing"
B Changing scope.
C Performing activities in parallel rather than in series.
D All of the above.
E A and C only.
D
QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
A Increase, decrease.
B Increase, increase
C Increase, increase or decrease.
D Decrease, decrease.
E Decrease, increase.
B
QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
A Allocation.
B Partitioning
C Leveling
D Quantification.
E None of above.
A
相關推薦:2012年pmp考試模擬試題及答案(四)
- 12015年咨詢工程師《咨詢概論》答疑:開標
- 22008年監(jiān)理工程師《建設工程合同管理》習題31
- 3造價工程師案例分析復習資料——建設工程招標投標
- 4混凝土輸送泵不能吸入空氣的原因
- 52015年咨詢工程師《項目決策分析與評價》每日一練10.31
- 62015年監(jiān)理工程師考試《合同管理》模擬練習(5)
- 7一級建造師管理與實務名詞解釋:通球掃線
- 8住建部公示甲級工程造價咨詢企業(yè)資質(zhì)延續(xù)通知
- 92015年安全工程師《安全生產(chǎn)法及相關法律知識》每日一練(4.12)
- 102015年招標師考試《法律法規(guī)與政策》知識點(13)
- 112008年監(jiān)理工程師《建設工程監(jiān)理案例分析》習題20
- 122015年咨詢工程師《工程咨詢概論》每日一練(5.10)
- 13名師達江解答二級建造師相關疑問——學習篇(一)
- 14催化重整裝置安全設施設置的考慮
- 15綠地綠化工程施工組織設計54p
- 162015年造價工程師《理論與法規(guī)》講義精髓(17)
- 17招標師法律法規(guī):國有土地使用權出讓
- 182013年二級建造師《建筑》:單位工程施工組織設計編制依據(jù)
- 19泛亞鐵路西線廣昆復線咽喉工程秀寧隧道貫通
- 202015年一級建造師《項目管理》精華知識點(16)
- 21攪拌車行車中跳擋分析原因以及如何應對
- 22【精品/實驗班】你的二建快速通關渠道
- 232015年咨詢工程師《宏觀經(jīng)濟政策與發(fā)展規(guī)劃》每日一練9.17
- 24PMP美國項目管理考試練習題及答案(十六)
- 252015年造價員安裝工程復習重點:外墻涂料特點
- 26《工程項目組織與管理》:施工進度
- 272015招標師考試項目管理與采購知識點:國際貿(mào)易的支付
- 28考前準備工作必不可少
- 29斜屋面防水工程施工技術
- 302015年招標師《專業(yè)實務》輔導:公路項目招標的內(nèi)容及監(jiān)管
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓